Construction · Synthetic Property 1
Schedule & Constraints
Control project schedule
The next three weeks of work. Anything in the way shows as a constraint; clear it before the start date or the activity slips.
| Activity | Project | Start | Finish | Company | In the way | Late start |
|---|---|---|---|---|---|---|
| A300 Partitions and board | PRJ-0001 | Oct 23 | Nov 1 | Northgate Drywall Co | Ready | — |
| A700 Lighting trim and controls | PRJ-0001 | Oct 30 | Nov 1 | Voltwise Electric | Material: MAT-003 LED downlights, 3000 K: Expected 2026-10-31, needed 2026-10-28 | — |
| A500 Paint | PRJ-0001 | Nov 2 | Nov 7 | — | Ready | — |
| A600 Flooring | PRJ-0001 | Nov 8 | Nov 15 | — | Ready | — |
| M900 Handover to the hotel | PRJ-0001 | Nov 16 | Nov 16 | — | Ready | — |