Schedule & Constraints
Control project schedule
| Code | Project | Activity | Days | Start | Finish | Float | Critical | Progress | Company |
|---|---|---|---|---|---|---|---|---|---|
| A100 | PRJ-0001 | Mobilize and protect finished areas | 2 | Oct 17 | Oct 18 | 0 | — | 100% | — |
| A200 | PRJ-0001 | Selective demolition | 4 | Oct 19 | Oct 22 | 0 | — | 100% | — |
| A300 | PRJ-0001 | Partitions and board | 10 | Oct 23 | Nov 1 | 0 | Yes | 50% | Northgate Drywall Co |
| A400 | PRJ-0001 | Electrical rough-in | 5 | Oct 25 | Oct 30 | 13 | — | 40% | Voltwise Electric |
| A700 | PRJ-0001 | Lighting trim and controls | 3 | Oct 31 | Nov 2 | 13 | — | 0% | Voltwise Electric |
| A500 | PRJ-0001 | Paint | 6 | Nov 2 | Nov 7 | 0 | Yes | 0% | — |
| A600 | PRJ-0001 | Flooring | 8 | Nov 8 | Nov 15 | 0 | Yes | 0% | — |
| M900 | PRJ-0001 | Handover to the hotel | ◆ | Nov 16 | Nov 16 | 0 | Yes | 0% | — |