Control project schedule

ActivityProjectAfterLinkLag (days)
A200 Selective demolitionPRJ-0001A100 Mobilize and protect finished areasFinish to start0
A300 Partitions and boardPRJ-0001A200 Selective demolitionFinish to start0
A400 Electrical rough-inPRJ-0001A300 Partitions and boardStart to start2
A700 Lighting trim and controlsPRJ-0001A400 Electrical rough-inFinish to start0
A500 PaintPRJ-0001A300 Partitions and boardFinish to start0
A600 FlooringPRJ-0001A500 PaintFinish to start0
M900 Handover to the hotelPRJ-0001A600 FlooringFinish to start0
M900 Handover to the hotelPRJ-0001A700 Lighting trim and controlsFinish to start0