Construction · Synthetic Property 1
Schedule & Constraints
Control project schedule
| Kind | Project | Constraint | Activity | Need by | Status |
|---|
| Material | PRJ-0001 | MAT-003 LED downlights, 3000 K: Expected 2026-10-31, needed 2026-10-28 | A700 | Oct 28 | Open |
| RFI | PRJ-0001 | RFI-001 Bulkhead height at corridor grid C | A300 | Oct 23 | Cleared |