A fixed earliest start, like a permit date.
CodeProjectActivityDaysStartFinishFloatCriticalProgressCompany
A100PRJ-0001Mobilize and protect finished areas2Oct 17Oct 180—100%—
A200PRJ-0001Selective demolition4Oct 19Oct 220—100%—
A300PRJ-0001Partitions and board10Oct 23Nov 10Yes50%Northgate Drywall Co
A400PRJ-0001Electrical rough-in5Oct 25Oct 3013—40%Voltwise Electric
A700PRJ-0001Lighting trim and controls3Oct 31Nov 213—0%Voltwise Electric
A500PRJ-0001Paint6Nov 2Nov 70Yes0%—
A600PRJ-0001Flooring8Nov 8Nov 150Yes0%—
M900PRJ-0001Handover to the hotel◆Nov 16Nov 160Yes0%—