Projected cost is what is committed plus what is left on the budget, adjusted by the project manager. A forecast 5% over the revised budget flags cost drift.

CodeProjectDescriptionRevisedCommittedUncommittedAdjustmentProjectedVariance
01-900PRJ-0001Contingency 5%$10,225.00$0.00$10,225.00$0.00$10,225.00$0.00
01-950PRJ-0001Overhead 3%$6,135.00$0.00$6,135.00$0.00$6,135.00$0.00
01-990PRJ-0001Fee 4%$8,834.40$0.00$8,834.40$0.00$8,834.40$0.00
02-4119PRJ-0001Selective interior demolition$21,600.00$0.00$21,600.00$0.00$21,600.00$0.00
09-2116PRJ-0001Gypsum board partition, 16 mm, metal stud$52,200.00$53,000.00$0.00$0.00$53,000.00-$800.00
09-3013PRJ-0001Porcelain floor tile, set and grouted$26,400.00$0.00$26,400.00$0.00$26,400.00$0.00
09-6813PRJ-0001Carpet tile, commercial grade$64,400.00$0.00$64,400.00$0.00$64,400.00$0.00
09-9123PRJ-0001Interior painting, two coats$20,700.00$0.00$20,700.00$0.00$20,700.00$0.00
26-5119PRJ-0001LED downlight, supplied and installed$19,200.00$18,400.00$800.00$0.00$19,200.00$0.00
09-6813PRJ-0003Rubber sports flooring$14,000.00$0.00$14,000.00$0.00$14,000.00$0.00
09-9123PRJ-0003Interior painting$18,000.00$0.00$18,000.00$0.00$18,000.00$0.00
01-900PRJ-0002Contingency 8%$3,769.60$0.00$3,769.60$0.00$3,769.60$0.00
02-4119PRJ-0002Selective interior demolition$720.00$0.00$720.00$0.00$720.00$0.00
23-3113PRJ-0002Galvanized ductwork, installed$8,400.00$0.00$8,400.00$0.00$8,400.00$0.00
23-7313PRJ-0002Packaged rooftop unit, 10 ton$38,000.00$0.00$38,000.00$0.00$38,000.00$0.00