| Number | Question | Decision | By | On | Impact |
|---|---|---|---|---|---|
| D-003 | CO-001 Lower corridor bulkhead to 2.30 m | Approved: $3,200.00, 2 days | Rowan Sitework | Oct 25 | Commitment |
| D-002 | RFI-001 Bulkhead height at corridor grid C | Drop the bulkhead to 2.30 m and frame around the duct. Revised A-201 to follow. | Architect of record | Oct 23 | Cost and Schedule |
| D-004 | Lobby feature wall finish | Walnut veneer panels, sample B. | Owner's representative | Oct 21 | No cost change; panels inside the allowance. |
| D-001 | SUB-001 rev 0 Gypsum board and framing product data | Approved: Approved as submitted. | Architect of record | Oct 15 | Materials |