Construction · Synthetic Property 1

Construction Projects

One project portfolio/selected-project board.

Record decision
Cost, schedule, scope, none
NumberProjectQuestionDecisionByOnImpact
D-003PRJ-0001CO-001 Lower corridor bulkhead to 2.30 mApproved: $3,200.00, 2 daysRowan SiteworkOct 25Commitment
D-002PRJ-0001RFI-001 Bulkhead height at corridor grid CDrop the bulkhead to 2.30 m and frame around the duct. Revised A-201 to follow.Architect of recordOct 23Cost and Schedule
D-004PRJ-0001Lobby feature wall finishWalnut veneer panels, sample B.Owner's representativeOct 21No cost change; panels inside the allowance.
D-001PRJ-0001SUB-001 rev 0 Gypsum board and framing product dataApproved: Approved as submitted.Architect of recordOct 15Materials
Decisions · Construction Projects · Hospitality Operating System