Construction · Synthetic Property 1

Schedule & Constraints

Control project schedule

The next three weeks of work. Anything in the way shows as a constraint; clear it before the start date or the activity slips.

ActivityStartFinishCompanyIn the wayLate start
A300 Partitions and boardOct 23Nov 1Northgate Drywall CoReady—
A700 Lighting trim and controlsOct 30Nov 1Voltwise ElectricMaterial: MAT-003 LED downlights, 3000 K: Expected 2026-10-31, needed 2026-10-28—
A500 PaintNov 2Nov 7—Ready—
A600 FlooringNov 8Nov 15—Ready—
M900 Handover to the hotelNov 16Nov 16—Ready—
Lookahead · Schedule & Constraints · Hospitality Operating System