Construction · Synthetic Property 1
Schedule & Constraints
Control project schedule
| Activity | After | Link | Lag (days) |
|---|---|---|---|
| A200 Selective demolition | A100 Mobilize and protect finished areas | Finish to start | 0 |
| A300 Partitions and board | A200 Selective demolition | Finish to start | 0 |
| A400 Electrical rough-in | A300 Partitions and board | Start to start | 2 |
| A700 Lighting trim and controls | A400 Electrical rough-in | Finish to start | 0 |
| A500 Paint | A300 Partitions and board | Finish to start | 0 |
| A600 Flooring | A500 Paint | Finish to start | 0 |
| M900 Handover to the hotel | A600 Flooring | Finish to start | 0 |
| M900 Handover to the hotel | A700 Lighting trim and controls | Finish to start | 0 |