Construction · Synthetic Property 1

Schedule & Constraints

Control project schedule

ActivityAfterLinkLag (days)
A200 Selective demolitionA100 Mobilize and protect finished areasFinish to start0
A300 Partitions and boardA200 Selective demolitionFinish to start0
A400 Electrical rough-inA300 Partitions and boardStart to start2
A700 Lighting trim and controlsA400 Electrical rough-inFinish to start0
A500 PaintA300 Partitions and boardFinish to start0
A600 FlooringA500 PaintFinish to start0
M900 Handover to the hotelA600 FlooringFinish to start0
M900 Handover to the hotelA700 Lighting trim and controlsFinish to start0
Dependencies · Schedule & Constraints · Hospitality Operating System