Construction · Synthetic Property 1

Schedule & Constraints

Control project schedule

Add activity
For example A100
A fixed earliest start, like a permit date.
CodeActivityDaysStartFinishFloatCriticalProgressCompany
A100Mobilize and protect finished areas2Oct 17Oct 180—100%—
A200Selective demolition4Oct 19Oct 220—100%—
A300Partitions and board10Oct 23Nov 10Yes50%Northgate Drywall Co
A400Electrical rough-in5Oct 25Oct 3013—40%Voltwise Electric
A700Lighting trim and controls3Oct 31Nov 213—0%Voltwise Electric
A500Paint6Nov 2Nov 70Yes0%—
A600Flooring8Nov 8Nov 150Yes0%—
M900Handover to the hotel◆Nov 16Nov 160Yes0%—