Project Financials

Control project cost and forecast

Funding
$260,000.00
Revised budget
$229,694.40
Committed
$71,400.00
Projected
$230,494.40
Paid
$16,650.00
Retainage held
$1,850.00

Projected cost is what is committed plus what is left on the budget, adjusted by the project manager. A forecast 5% over the revised budget flags cost drift.

CodeDescriptionRevisedCommittedUncommittedAdjustmentProjectedVariance
01-900Contingency 5%$10,225.00$0.00$10,225.00$0.00$10,225.00$0.00
01-950Overhead 3%$6,135.00$0.00$6,135.00$0.00$6,135.00$0.00
01-990Fee 4%$8,834.40$0.00$8,834.40$0.00$8,834.40$0.00
02-4119Selective interior demolition$21,600.00$0.00$21,600.00$0.00$21,600.00$0.00
09-2116Gypsum board partition, 16 mm, metal stud$52,200.00$53,000.00$0.00$0.00$53,000.00-$800.00
09-3013Porcelain floor tile, set and grouted$26,400.00$0.00$26,400.00$0.00$26,400.00$0.00
09-6813Carpet tile, commercial grade$64,400.00$0.00$64,400.00$0.00$64,400.00$0.00
09-9123Interior painting, two coats$20,700.00$0.00$20,700.00$0.00$20,700.00$0.00
26-5119LED downlight, supplied and installed$19,200.00$18,400.00$800.00$0.00$19,200.00$0.00