Construction · Synthetic Property 1
Project Financials Control project cost and forecast
Projected cost is what is committed plus what is left on the budget, adjusted by the project manager. A forecast 5% over the revised budget flags cost drift.
Code Description Revised Committed Uncommitted Adjustment Projected Variance 09-6813 Rubber sports flooring $14,000.00 $0.00 $14,000.00 $0.00 $14,000.00 $0.00 09-9123 Interior painting $18,000.00 $0.00 $18,000.00 $0.00 $18,000.00 $0.00
PRJ-0003 09-6813 · Rubber sports flooring ✕
Original $14,000.00
Approved changes $0.00
Pending changes $0.00
Revised $14,000.00
Committed $0.00
Cost to date $0.00
Forecast adjustment $0.00
Projected $14,000.00
Variance $0.00
Source Manual Commitments Nothing committed on this line yet.
Change orders No change orders on this line.
History 2026-09-19 15:00 budget.line_create · Jordan Buildwell