Construction · Synthetic Property 1
RFIs, Submittals & Changes
Formalize project questions and impact decisions
| Number | Project | Title | Origin | Estimate | Days | Status |
|---|---|---|---|---|---|---|
| CE-001 | PRJ-0001 | RFI-001 Bulkhead height at corridor grid C | RFI | $3,200.00 | 2 | Converted |
Formalize project questions and impact decisions
| Number | Project | Title | Origin | Estimate | Days | Status |
|---|---|---|---|---|---|---|
| CE-001 | PRJ-0001 | RFI-001 Bulkhead height at corridor grid C | RFI | $3,200.00 | 2 | Converted |